SB 0278 DNR to issue water qual. certif. w/in 90 days of pub. notice
Sponsor:EHLMANN
Committee:AGRILR Number:S1081.01I
Last Action:02/08/95 - Hearing Conducted S Agriculture & Local Government Committee
Title:
Effective Date:August 28, 1995
All Actions | Senate Home Page | List of 1995 Senate Bills
Current Bill Summary

SB 278 - Permit approval from the U. S. Army Corps of Engineers is required under Section 404 of the Federal Clean Water Act for dredging and filling or other discharges to the waters of the United States, including wetlands. This act requires the Missouri Department of Natural Resources to issue or deny water quality certification required under Section 401 of the Clean Water Act for Section 404 permits within 90 days of issuance of the joint public notice. If the DNR fails to act within that time, water quality certification shall be deemed issued. Section 404 permit approval from the U. S. Army Corps of Engineers will still be required.
TOM CRAWFORD