SECOND REGULAR SESSION

[I N T R O D U C E D]

SENATE BILL NO. 701

88th GENERAL ASSEMBLY


S2222.01I

AN ACT

To repeal section 260.205, RSMo Supp. 1995, relating to environmental control, and to enact in lieu thereof one new section relating to the same subject.


BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF MISSOURI,

AS FOLLOWS:

Section A. Section 260.205, RSMo Supp. 1995, is repealed and one new section enacted in lieu thereof, to be known as section 260.205, to read as follows:

260.205. 1. On and after January 1, 1996, it shall be unlawful for any person to operate a solid waste processing facility or solid waste disposal area of a solid waste management system without first obtaining an operating permit from the department. On and after January 1, 1996, it shall be unlawful for any person to construct a solid waste processing facility or solid waste disposal area without first obtaining a construction permit from the department pursuant to this section. A current authorization to operate issued by the department pursuant to sections 260.200 to 260.345 shall be considered to be a permit to operate for purposes of this section for all solid waste disposal areas and processing facilities existing on August 28, 1995. A permit shall not be issued for a sanitary landfill to be located in a flood area, as determined by the department, where flood waters are likely to significantly erode final cover. In order to protect the purity and cleanliness of drinking water, no permit shall be issued for a sanitary landfill that is to be located within two miles of any unconfined water aquifer which is the primary source of human drinking water of a municipality with over one hundred thousand inhabitants. A permit shall not be required to operate a waste stabilization lagoon, settling pond or other water treatment facility which has a valid permit from the Missouri clean water commission even though the facility may receive solid or semisolid waste materials.

2. On and after January 1, 1996, no person or operator may apply for or obtain a permit to construct a solid waste disposal area unless the person has requested the department to conduct a preliminary site investigation and obtained preliminary approval from the department. The department shall, within sixty days of such request, conduct a preliminary investigation and approve or disapprove the site.

3. On and after January 1, 1996, no person may apply for or obtain a permit to construct a solid waste disposal area unless the person has submitted to the department a plan for conducting a detailed surface and subsurface geologic and hydrologic investigation and has obtained geologic and hydrologic site approval from the department. The department shall approve or disapprove the plan within thirty days of receipt. The applicant shall conduct the investigation pursuant to the plan and submit the results to the department. The department shall provide approval or disapproval within sixty days of receipt of the investigation results.

4. (1) Every person desiring to construct a solid waste processing facility or solid waste disposal area shall make application for a permit on forms provided for this purpose by the department. Every applicant shall submit evidence of financial responsibility with the application. Any applicant who relies in part upon a parent corporation for this demonstration shall also submit evidence of financial responsibility for that corporation and any other subsidiary thereof.

(2) Every applicant shall provide a financial assurance instrument or instruments to the department prior to the granting of a construction permit for a solid waste disposal area. The financial assurance instrument or instruments shall be irrevocable, meet all requirements established by the department and shall not be canceled, revoked, disbursed, released or allowed to terminate without the approval of the department. After the cessation of active operation of a sanitary landfill, or other solid waste disposal area as designed by the department, neither the guarantor nor the operator shall cancel, revoke or disburse the financial assurance instrument or allow the instrument to terminate until the operator is released from post-closure monitoring and care responsibilities pursuant to section 260.227.

(3) The applicant for a permit to construct a solid waste disposal area shall provide the department with plans, specifications, and such other data as may be necessary to comply with the purpose of sections 260.200 to 260.345. The application shall demonstrate compliance with all applicable local planning and zoning requirements. The department shall make an investigation of the solid waste disposal area and determine whether it complies with the provisions of sections 260.200 to 260.345 and the rules and regulations adopted under sections 260.220 to 260.345. Within twelve consecutive months of the receipt of an application for a construction permit the department shall approve or deny the application. The department shall issue rules and regulations establishing time limits for permit modifications and renewal of a permit for a solid waste disposal area. The time limit shall be consistent with this chapter.

(4) The applicant for a permit to construct a solid waste processing facility shall provide the department with plans, specifications and such other data as may be necessary to comply with the purpose of sections 260.200 to 260.345. Within one hundred eighty days of receipt of the application, the department shall determine whether it complies with the provisions of sections 260.200 to 260.345. Within twelve consecutive months of the receipt of an application for a permit to construct an incinerator as defined in section 260.200 or a material recovery facility as defined in section 260.200, and within six months for permit modifications, the department shall approve or deny the application. Permits issued for solid waste facilities shall be for the anticipated life of the facility.

(5) If the department fails to approve or deny an application for a permit or a permit modification within the time limits specified in subdivisions (3) and (4) of this subsection, the applicant may maintain an action in the circuit court of Cole County or that of the county in which the facility is located or is to be sited. The court shall order the department to show cause why it has not acted on the permit and the court may, upon the presentation of evidence satisfactory to the court, order the department to issue or deny such permit or permit modification. Permits for solid waste disposal areas, whether issued by the department or ordered to be issued by a court, shall be for the anticipated life of the facility.

(6) The applicant for a permit to construct a solid waste processing facility shall pay an application fee of one thousand dollars. Upon completion of the department's evaluation of the application, but before receiving a permit, the applicant shall reimburse the department for all reasonable costs incurred by the department up to a maximum of four thousand dollars. The applicant for a permit to construct a solid waste disposal area shall pay an application fee of two thousand dollars. Upon completion of the department's evaluations of the application, but before receiving a permit, the applicant shall reimburse the department for all reasonable costs incurred by the department up to a maximum of eight thousand dollars. Applicants who withdraw their application before the department completes its evaluation shall be required to reimburse the department for costs incurred in the evaluation. The department shall not collect the fees authorized in this subdivision unless it complies with the time limits established in this section.

(7) When the review reveals that the facility or area does conform with the provisions of sections 260.200 to 260.345 and the rules and regulations adopted under sections 260.200 to 260.345, the department shall approve the application and shall issue a permit for the construction of each solid waste processing facility or solid waste disposal area as set forth in the application and with any permit terms and conditions which the department deems appropriate. In the event that the facility or area fails to meet the rules and regulations adopted pursuant to sections 260.200 to 260.345, the department shall issue a report to the applicant stating the reason for denial of a permit.

5. Plans, designs, and relevant data for the construction of solid waste processing facilities and solid waste disposal areas shall be submitted to the department by a registered professional engineer licensed by the state of Missouri for approval prior to the construction, alteration or operation of such a facility or area.

6. Any person or operator as defined in section 260.200 who intends to obtain a construction permit in a solid waste management district with an approved solid waste management plan shall request a recommendation in support of the application from the executive board created in section 260.315. The executive board shall consider the impact of the proposal on, and the extent to which the proposal conforms to, the approved district solid waste management plan prepared pursuant to section 260.325. The executive board shall act upon the request for a recommendation within sixty days of receipt and shall submit a resolution to the department specifying its position and its recommendation regarding conformity of the application to the solid waste plan. The board's failure to submit a resolution constitutes recommendation of the application. The department may consider the application, regardless of the board's action thereon and may deny the construction permit if the application fails to meet the requirements of sections 260.200 to 260.345, or if the application is inconsistent with the district's solid waste management plan.

7. If the site proposed for a solid waste disposal area is not owned by the applicant, the owner or owners of the site shall acknowledge that an application under sections 260.200 to 260.345 is to be submitted by signature or signatures thereon. The department shall provide the owner with copies of all communication with the operator, including inspection reports and orders issued pursuant to section 260.230.

8. The department shall not issue a permit for the operation of a solid waste disposal area designed to serve a city with a population of greater than four hundred thousand located in more than one county, if the site is located within one-half mile of an adjoining municipality, without the approval of the governing body of such municipality. The governing body shall conduct a public hearing within fifteen days of notice, shall publicize the hearing in at least one newspaper having general circulation in the municipality, and shall vote to approve or disapprove the land disposal facility within thirty days after the close of the hearing.

9. Upon receipt of an application for a permit to construct a solid waste processing facility or disposal area, the department shall notify the public of such receipt:

(1) By legal notice published in a newspaper in the area of the proposed disposal area or processing facility;

(2) By certified mail to the governing body of the county or city in which the proposed disposal area or processing facility is to be located; and

(3) By mail to the last known address of all record owners of contiguous real property or real property located within one thousand feet of the proposed disposal area and, for a proposed processing facility, notice as provided in section 64.875, RSMo, or section 89.060, RSMo, whichever is applicable. A public hearing shall be held in the county in which the proposed solid waste disposal area is to be located.

10. After the issuance of a construction permit for a solid waste disposal area, but prior to the beginning of disposal operations, the owner and the department shall execute an easement to allow the department, its agents or its contractors to enter the premises to complete work specified in the closure plan, or to monitor or maintain the site or to take remedial action during the post-closure period. After issuance of a construction permit for a solid waste disposal area, but prior to the beginning of disposal operations, the owner shall submit evidence that he has recorded, in the office of the recorder of deeds in the county where the disposal area is located, a notice and covenant running with the land that the property has been permitted as a solid waste disposal area and prohibits use of the land in any manner which interferes with the closure and, where appropriate, post-closure plans filed with the department.

11. On and after January 1, 1996, every person desiring to obtain a permit to operate a solid waste disposal area or processing facility shall submit applicable information and apply for an operating permit from the department. The department shall review the information and determine, within sixty days of receipt, whether it complies with the provisions of sections 260.200 to 260.345 and the rules and regulations adopted under sections 260.220 to 260.345. When the review reveals that the facility or area does conform with the provisions of sections 260.200 to 260.345 and the rules and regulations adopted under sections 260.200 to 260.345, the department shall issue a permit for the operation of each solid waste processing facility or solid waste disposal area and with any permit terms and conditions which the department deems appropriate. In the event that the facility or area fails to meet the rules and regulations adopted pursuant to sections 260.200 to 260.345, the department shall issue a report to the applicant stating the reason for denial of a permit.

12. Each solid waste disposal area, except utility waste landfills unless otherwise and to the extent required by the department, and those solid waste processing facilities designated by rule, shall be operated under the direction of a certified solid waste technician in accordance with sections 260.200 to 260.345 and the rules and regulations promulgated under sections 260.200 to 260.345.

13. Base data for the quality and quantity of groundwater in the solid waste disposal area shall be collected and submitted to the department prior to the operation of a new or expansion of an existing solid waste disposal area. Base data shall include a chemical analysis of groundwater drawn from the proposed solid waste disposal area.

14. Leachate collection and removal systems shall be incorporated into new or expanded sanitary landfills which are permitted after August 13, 1986. The department shall assess the need for a leachate collection system for all types of solid waste disposal areas, other than sanitary landfills, and the need for monitoring wells when it evaluates the application for all new or expanded solid waste disposal areas. The department may require an operator of a solid waste disposal area to install a leachate collection system before the beginning of disposal operations, at any time during disposal operations for unfilled portions of the area, or for any portion of the disposal area as a part of a remedial plan. The department may require the operator to install monitoring wells before the beginning of disposal operations or at any time during the operational life or post-closure care period if it concludes that conditions at the area warrant such monitoring. The operator of a demolition landfill or utility waste landfill shall not be required to install a leachate collection and removal system or monitoring wells unless otherwise and to the extent the department so requires based on hazardous waste characteristic criteria or site specific geohydrological characteristics or conditions.

15. Permits granted by the department, as provided in sections 260.200 to 260.345, shall be subject to suspension for a designated period of time, civil penalty or revocation whenever the department determines that the solid waste processing facility or solid waste disposal area is, or has been, operated in violation of sections 260.200 to 260.345 or the rules or regulations adopted pursuant to sections 260.200 to 260.345, or has been operated in violation of any permit terms and conditions, or is creating a public nuisance, health hazard, or environmental pollution. In the event a permit is suspended or revoked, the person named in the permit shall be fully informed as to the reasons for such action.

16. Each permit for operation of a facility or area shall be issued only to the person named in the application. Permits are transferable as a modification to the permit. An application to transfer ownership shall identify the proposed permittee. A disclosure statement for the proposed permittee listing violations contained in subsection 19 of this section shall be submitted to the department. The operation and design plans for the facility or area shall be updated to provide compliance with the currently applicable law and rules. A financial assurance instrument in such an amount and form as prescribed by the department shall be provided for solid waste disposal areas by the proposed permittee prior to transfer of the permit. The financial assurance instrument of the original permittee shall not be released until the new permittee's financial assurance instrument has been approved by the department and the transfer of ownership is complete.

17. Those solid waste disposal areas permitted on January 1, 1996, shall, upon submission of a request for permit modification, be granted a solid waste management area operating permit if the request meets reasonable requirements set out by the department. Any permit application received under this section prior to January 1, 1996, shall be reviewed under sections 260.200 to 260.345, as those sections existed immediately prior to August 28, 1995.

18. In case a permit required under this section is denied or revoked, the person may request a hearing in accordance with section 260.235.

19. Any person seeking a permit or renewal of a permit to operate a commercial solid waste processing facility, or a solid waste disposal area shall, concurrently with the filing of application for a permit, file a disclosure statement with the department of natural resources. The disclosure statement shall include, but not be limited to, a listing of any felony convictions by state or federal agencies, and a listing of other enforcement actions, sanctions, permit revocations or denials by any state or federal authority of every person seeking a permit, including officers, directors, partners and facility or location managers of each person seeking a permit, any violations of Missouri environmental statutes, violations of the environmental statutes of other states or federal statutes and a listing of convictions for any crimes or criminal acts, an element of which involves restraint of trade, price-fixing, intimidation of the customers of another person or for engaging in any other acts which may have the effect of restraining or limiting competition concerning activities regulated under this chapter or similar laws of other states or the federal government; except that convictions for violations by entities purchased or acquired by an applicant or permittee which occurred prior to the purchase or acquisition shall not be included. The department shall by rule, define those environmental violations which must be reported pursuant to this section. For purposes of this section, additional persons as required by rule shall be named in the statement and violations or convictions of such persons shall be listed. The department or its representative shall verify the information provided on the disclosure statement prior to permit issuance. The disclosure statement shall be used by the department in determining whether a permit should be granted or denied on the basis of the applicant's status as a habitual violator; however, the department has the authority to make a habitual violator determination independent of the information contained in the disclosure statement. After permit issuance, each facility shall annually file an updated disclosure statement with the department of natural resources on or before March thirty-first of each year. Any county, district, municipality, authority or other political subdivision of this state which owns and operates a sanitary landfill shall be exempt from the provisions of this subsection.

20. Any person seeking a permit to operate a solid waste disposal area, a solid waste processing facility or a resource recovery facility shall, concurrently with the filing of the application for a permit, disclose any convictions in this state of municipal or county public health or land use ordinances related to the management of solid waste. If the department finds that there has been a continuing pattern of serious adjudicated violations by the applicant, the department may deny the application.

21. No permit to construct or permit to operate shall be required under this section for any utility waste landfill located in a county of the third classification with a township form of government which adjoins another state and which has a population of at least ten thousand inhabitants and no more than twelve thousand five hundred inhabitants according to the most recent decennial census, if such utility waste landfill complies with all design and operating standards and closure requirements applicable to utility waste landfills under sections 260.200 to 260.345 and provided that no waste disposed of at such utility waste landfill is considered hazardous waste under the Missouri hazardous waste law.